Free CompTIA PK0-004 Exam Actual Questions

The questions for PK0-004 were last updated On Apr 29, 2025

At ValidExamDumps, we consistently monitor updates to the CompTIA PK0-004 exam questions by CompTIA. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the CompTIA Project+ exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by CompTIA in their CompTIA PK0-004 exam. These outdated questions lead to customers failing their CompTIA Project+ exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the CompTIA PK0-004 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

A project has activities on the critical path that must be completed before other activities can start:

Task A is dependent on Task C before Task D can be completed.

Task A requires Task B to start.

Task B takes twice as long to complete as Task C.

Which of the following is the appropriate ordering of the critical path?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

An organization has multiple projects that are taking place simultaneously.

Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

Show Answer Hide Answer
Correct Answer: D, E

Question No. 4

Stakeholders often do not understand the hierarchy of roles and responsibilities on a project team. Which of the following could provide a visual representation?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

A task on the critical path has just been completed. The project manager has been informed that the person

responsible for the next task has gone on an approved leave. Which of the following types of organizational

structure does this scenario BEST describe?

Show Answer Hide Answer
Correct Answer: D