Free Scrum PSK-I Exam Actual Questions

The questions for PSK-I were last updated On Dec 15, 2025

At ValidExamDumps, we consistently monitor updates to the Scrum PSK-I exam questions by Scrum. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the Scrum Professional Scrum with Kanban exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by Scrum in their Scrum PSK-I exam. These outdated questions lead to customers failing their Scrum Professional Scrum with Kanban exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the Scrum PSK-I exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

What is Kanban?

(choose the best answer)

Show Answer Hide Answer
Correct Answer: B

Kanban is:

* A strategy for optimizing the flow of value through a process (Option B): Kanban focuses on improving flow and efficiency by using a visual pull system with limited WIP. This strategy helps teams balance demand against throughput and enhance productivity by limiting the number of work items in progress.

Options A (methodology for visualizing workflow) and C (set of practices additive to Scrum) are partially correct but do not fully capture Kanban's purpose. Kanban is not just a visualization tool (A), and while it can be additive to Scrum (C), it is fundamentally a flow-based strategy


Question No. 2

Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?

(choose the best two answers)

Show Answer Hide Answer
Correct Answer: A, B

During a flow-based Daily Scrum, the team is likely to review metrics such as Work Item Age and Work in Progress (WIP):

* Work Item Age: Helps to identify items that have been in progress for a longer time than expected, signaling possible impediments or the need for swarming to complete those items.

* Work in Progress (WIP): Indicates the number of items currently being worked on, ensuring that the team is not exceeding the agreed WIP limits, which is crucial for maintaining a steady flow


Question No. 3

Which of the following are flow metrics needed when doing Scrum with Kanban?

(choose the best four answers)

Show Answer Hide Answer
Correct Answer: A, B, C, D

The essential flow metrics for Scrum Teams utilizing Kanban are:

Throughput: Measures the number of items completed within a time period.

Lead Time: Time from when an item enters the system to when it exits.

Cycle Time: Time it takes to complete a work item once it starts.

Work in Progress (WIP): The number of items currently in progress but not completed.

These metrics are foundational in understanding and optimizing flow within Kanban systems used alongside Scrum. 'Work Item Age' and 'Cumulative Flow Diagram (CFD)' are useful metrics but are not listed as primary flow metrics in Kanban for Scrum Teams.


Question No. 4

Little's Law states that:

(choose the best answer)

Show Answer Hide Answer
Correct Answer: A

Little's Law states:

* Average Cycle Time = Average Work in Progress (WIP) / Average Throughput.

Little's Law is used to understand and forecast the performance of a workflow system. It implies that if you know two of these three variables (Cycle Time, WIP, Throughput), you can calculate the third. The correct formula is Option A(

Options B, C, and D do not correctly state Little's Law.


Question No. 5

What are the two things that constitute a Kanban board?

(Choose the best two answers)

Show Answer Hide Answer
Correct Answer: B, C

A Kanban board is primarily used for visualizing the Workflow and managing WIP Limits. This visualization helps Scrum Teams make the flow of work transparent, track progress, and manage bottlenecks effectively. Limiting WIP ensures a pull-based flow, where new tasks are only started when there is available capacity, preventing overburdening the team. Reference: The Kanban Guide for Scrum Teams.