Question No. 1

You want to use the function "Read PP master data" in the production order.

However, while calling the function you receive an error message.

What could be the reason?

Show Answer Hide Answer
Correct Answer: B

Question No. 2

Which objects can affect the calculation of capacity requirements for an operation? (Choose three)

Show Answer Hide Answer
Correct Answer: A, D, E

Question No. 3

In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.

What does a firming type define? (Choose two)

Show Answer Hide Answer
Correct Answer: B, D

Question No. 4

Which of the following scheduling types can only be used in capacity planning?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)

Show Answer Hide Answer
Correct Answer: A, D, E