At ValidExamDumps, we consistently monitor updates to the PRINCE2-Foundation exam questions by PRINCE2. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PRINCE2 PRINCE 2 Foundation (6th Edition) exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PRINCE2 in their PRINCE2-Foundation exam. These outdated questions lead to customers failing their PRINCE2 PRINCE 2 Foundation (6th Edition) exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PRINCE2-Foundation exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Which is a purpose of the quality theme?

Show Answer Hide Answer
Correct Answer: A

Question No. 2

Which is a true statement about PRINCE2 event-driven controls?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

Which are characteristics of stakeholders?

1. They are often affected by the project

2. They agree with every project objective

3. They are only/always external to the corporate organization

4. They typically interact with the project

Show Answer Hide Answer