Free PMI PMI-SP Exam Practice Questions & Explanations

Last updated on: Nov 16, 2026
Prepared & Reviewed by the ValidExamDumps Editorial Team

At ValidExamDumps, we consistently monitor updates to the PMI-SP exam questions by PMI. Whenever our team identifies changes in the exam questions, objectives, focus areas or requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these up to date and 100% exam domain coverage questions, our customers can successfully pass the PMI Scheduling Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI-SP exam. These outdated questions lead to customers failing their PMI Scheduling Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions. Our main priority is your success in the PMI-SP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question 1

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's schedule variance?

Answer Options
Correct Answer: C
Explanation

he schedule variance can be found by subtracting the planned value form the earned value. In this instance, it is $2,025,000 minus $2,250,000. SV = 2,025,000 - 2,250,000 = -225,000 Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. Answer option A is incorrect. This is the cost variance for the project. Answer option B is incorrect. 13 percent is not a valid answer. Answer option D is incorrect. This is not a valid variance for this question; variances are typically negative numbers.

Question 2

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is

currently 40 percent complete, though it

was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management

would like to know if there is a schedule

variance. What is the planned value for this project?

Answer Options
Correct Answer: C
Explanation

The planned value is the percentage of where the project should be times the budget at

completion. In this instance, it is 45 percent of the

$950,000. Here, it can be calculated as follows:

PV = 45% of BAC

= 0.45 * 950,000

= 427,500

Planned value (PV) is the authorized budget assigned to the schedule work to be accomplished for a

schedule activity or work breakdown

structure component. It serves as a baseline against which actual performance is measured. The

theory of planned value is of vital importance

to the project management team and it is important to keep careful track of this. The term planned

value can also be in some situations

referred to by the project management team and the project management team leader as the

budgeted cost of work scheduled (BCWS).

Answer option A is incorrect. -$47,500 is the schedule variance (SV = EV-PV).

Answer option B is incorrect. This is the schedule performance index (SPI = EV/PV).

Answer option D is incorrect. This is the cost performance index (CPI = EV/AC).

Question 3

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index?

Answer Options
Correct Answer: C
Explanation

The schedule performance index shows how well the project is performing on its schedule goals. The SPI can be found by dividing the earned value by the planned value. In this instance, it is $2,025,000 divided by $2,250,000 for .90. The closer to 1, the better the performance. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula: SPI = Earned Value (EV) / Planned Value (PV) If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target. Answer option B is incorrect. 0.98 is the cost performance index. Answer option A is incorrect. 1.02 is the to-complete performance index. Answer option D is incorrect. -$108,120 is the variance at completion based on current performance.

Question 4

You are the project manager of the NNN Project. Stakeholders in the two-year project have

requested to send status reports to them via email every week. You have agreed and are sending the

reports on each Thursday. After six months of the project, the stakeholders are pleased with the

project progress and they would like you to reduce the status reports to every two weeks. What

process will examine the change to this project process and implement it in the project?

Answer Options
Correct Answer: B
Explanation

Although this appears to be a simple change the project manager must still follow the

rules of the project's change control system. Perform

Integrated Change Control is the process of reviewing all change requests, approving changes, and

controlling changes to the deliverables

and organizational process assets in a project. Perform Integrated Change Control has to do with

influencing the things that cause change,

determining that the change is required or has happened, and managing the change.

Answer option D is incorrect. Communications management is the execution of the communications

management plan.

Answer option A is incorrect. The project change control process not valid as it's the parent of the

integrated change control process, which is

more accurate for this question.

Answer option C is incorrect. Configuration management is the documentation and control of the

product's features and functions.

Question 5

Which organizational theory explains the factors that promote performance of people in any organization?

Answer Options
Correct Answer: A
Explanation

Herzberg's Motivation-Hygiene Theory, also known as Two Factor Theory, was developed by Frederick Herzberg, a psychologist who found that job satisfaction and job dissatisfaction acted independently of each other. Two Factor Theory states that there are certain factors in the workplace that cause job satisfaction, while a separate set of factors cause dissatisfaction. Two Factor Theory distinguishes between the following: Motivators (e.g. challenging work, recognition, responsibility) which give positive satisfaction, arising from intrinsic conditions of the job itself, such as recognition, achievement, or personal growth. Hygiene factors (e.g. status, job security, salary and fringe benefits) which do not give positive satisfaction, although dissatisfaction results from their absence. These are extrinsic to the work itself, and include aspects, such as company policies, supervisory practices, or wages/salary. Essentially, hygiene factors are needed to ensure an employee is not dissatisfied. Motivation factors are needed in order to motivate an employee to higher performance, Herzberg also further classified our actions and how and why we do them, for example, if you perform a work-related action because you have to, then that is classed as movement, but if you perform a work-related action because you want to, then that is classed as motivation. Answer option C is incorrect. McGregor's X and Y theory describes the team members and their behavior on the project and how management responds. Answer option B is incorrect. It describes the five layer of needs we all have. Answer option D is incorrect. It explains the processes that an individual undergoes to make choices.