Free PMI PMI-SP Exam Actual Questions

The questions for PMI-SP were last updated On Dec 16, 2025

At ValidExamDumps, we consistently monitor updates to the PMI-SP exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Scheduling Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI-SP exam. These outdated questions lead to customers failing their PMI Scheduling Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI-SP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

Show Answer Hide Answer
Correct Answer: D

The schedule performance index can be found by dividing the earned value by the planned value. In this project, it's $447,000 divided by the $558,750 for a value of 0.80. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.

Answer option A is incorrect. '80' is not the same value as '.80'. Answer option B is incorrect. 1.02 is the cost performance index. Answer option C is incorrect. 102 is not a valid calculation for this question.


Question No. 2

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is

currently 40 percent complete, though it

was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management

would like to know if there is a schedule

variance. What is the planned value for this project?

Show Answer Hide Answer
Correct Answer: C

The planned value is the percentage of where the project should be times the budget at

completion. In this instance, it is 45 percent of the

$950,000. Here, it can be calculated as follows:

PV = 45% of BAC

= 0.45 * 950,000

= 427,500

Planned value (PV) is the authorized budget assigned to the schedule work to be accomplished for a

schedule activity or work breakdown

structure component. It serves as a baseline against which actual performance is measured. The

theory of planned value is of vital importance

to the project management team and it is important to keep careful track of this. The term planned

value can also be in some situations

referred to by the project management team and the project management team leader as the

budgeted cost of work scheduled (BCWS).

Answer option A is incorrect. -$47,500 is the schedule variance (SV = EV-PV).

Answer option B is incorrect. This is the schedule performance index (SPI = EV/PV).

Answer option D is incorrect. This is the cost performance index (CPI = EV/AC).


Question No. 3

You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:

Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

Show Answer Hide Answer
Correct Answer: D

If Activity D increases by six days, the duration of the project will not change. There is 11 days of float available for Activity D so it may delay by six days without affecting the project end date. What is float? Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options A, B, and C are incorrect. These are not valid answers for the question.


Question No. 4

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

Show Answer Hide Answer
Correct Answer: C

The schedule performance index is found by dividing the earned value by the planned value. For

Holly's project, it would be as follows:

SPI = EV/PV

= (0.85*9,850,400)/(0.95*9,850,400)

=8,372,840/9,357,880

=0.89

Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in

trend analysis to predict future performance.

SPI is the ratio of earned value to planned value. The SPI is calculated based on the following

formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The SPI value of 1 indicates that the project is right on target.

Answer option D is incorrect. Ten percent is not a valid calculation for this question.

Answer option B is incorrect. 0.98 is the cost performance index.

Answer option A is incorrect. 1.07 is the to-complete performance index based on the BAC.


Question No. 5

Ned is the project manager for his organization. Ned is using a standard tool to capture, store, and distribute information to the stakeholders about the project costs, schedule, and performance. What term is assigned to this communication tool?

Show Answer Hide Answer
Correct Answer: C

This is simply an example of a reporting system. It can be part of the project

management information system, but for your examination, the

PMBOK acknowledges this tool directly as part of project performance reporting.

Reporting system is a tool and technique used for reporting performance. It is a standard means to

store, capture, and give out the

information to the stakeholders about the project costs, performance, and schedule.

Answer option A is incorrect. The project management information system does more than just

communicating the performance. It is a tool to

help the project manager plan and monitor the project.

Answer option D is incorrect. The PMBOK does not mention a communications management system.

Answer option B is incorrect. Table reporting is one output of a reporting system, not the entire

system.