Free PMI PMI-RMP Exam Actual Questions

The questions for PMI-RMP were last updated On Apr 27, 2025

At ValidExamDumps, we consistently monitor updates to the PMI-RMP exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Risk Management Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI-RMP exam. These outdated questions lead to customers failing their PMI Risk Management Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI-RMP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

A project manager has determined that an activity is too complex to complete internally so they hire a licensed contractor to complete the work. What is the project manager performing in this situation?

Show Answer Hide Answer
Correct Answer: B

By hiring a licensed contractor to complete the complex activity, the project manager is transferring the risk associated with that activity to the contractor. This is an example of risk transfer, as the responsibility for managing the risk is shifted from the project manager to the contractor.

According to the PMI Risk Management Professional (PMI-RMP) Handbook1, one of the domains of the PMI-RMP exam isRisk Response Planning, which involves developing options and actions to enhance opportunities and reduce threats to project objectives1.One of the strategies for negative risks or threats isrisk transfer, which involves shifting the impact of a threat to a third party, such as a contractor, a vendor, or an insurer2. In this situation, the project manager is performing risk transfer by hiring a licensed contractor to complete the work that is too complex to complete internally. By doing so, the project manager is transferring the responsibility and liability of the activity to the contractor, who is expected to have the expertise and resources to handle the complexity.The project manager is not performing risk mitigation, which involves reducing the probability and/or impact of a threat2.The project manager is not performing risk acceptance, which involves acknowledging the existence of a threat and making a conscious decision to accept it without taking any action2.The project manager is not performing risk avoidance, which involves changing the project plan to eliminate the threat or protect the project objectives from its impact2.Reference:1: PMI Risk Management Professional (PMI-RMP) Handbook, page 62: A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Sixth Edition, page 436.


Question No. 2

After presenting a list of risks to the major project stakeholders and project sponsor, the board requested the risks be sorted differently from the results presented by the project team. This is a major issue and will cause a 2-week delay in the project.

How could the risk manager have avoided the board's response?

Show Answer Hide Answer
Correct Answer: A

According to the PMBOK Guide, risk prioritization is the process of assigning a level of importance to each identified risk based on its probability and impact, as well as other factors such as urgency, stakeholder tolerance, and project objectives. Risk prioritization helps the project team to focus on the most significant risks and allocate resources accordingly. One of the tools and techniques for risk prioritization is stakeholder engagement, which involves involving the key stakeholders in the risk analysis and decision making process. Stakeholder engagement helps to ensure that the risk prioritization reflects the expectations and preferences of the stakeholders, and that they are aware of and agree with the results. By engaging the key stakeholders during the prioritization process, the risk manager could have avoided the board's request to sort the risks differently, as the board would have been part of the process and would have accepted the outcome.Reference: = PMBOK Guide, 6th edition, pages 406-407; The Standard for Risk Management in Portfolios, Programs, and Projects, page 67.


Question No. 3

A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.

How should the risk manager explain the need for a risk strategy specific to this project?

Show Answer Hide Answer
Correct Answer: D

Question No. 4

A risk manager is working on the risk management plan for a new digital platform and realizes the project sponsor who is the IT manager has not been invited to the project team meetings. The IT manager is concerned that the IT infrastructure is unable to host the new platform the team is creating. The risk manager asks the IT manager to be included in the meetings

What should the IT manager's role be in the project team meetings'?

Show Answer Hide Answer
Correct Answer: D