Free PMI PMI-PBA Exam Actual Questions

The questions for PMI-PBA were last updated On May 5, 2024

Question No. 1

A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.

At this point, the business analyst should first:

Show Answer Hide Answer
Correct Answer: D

Question No. 2

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

Show Answer Hide Answer
Correct Answer: D

Question No. 3

After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?

Show Answer Hide Answer
Correct Answer: D

Question No. 4

Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company's performance and profitability.

Which of the following should have been implemented to ensure that the projects would improve the company's performance and profitability?

Show Answer Hide Answer
Correct Answer: D

Question No. 5

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

Show Answer Hide Answer
Correct Answer: B