Free PMI PgMP Exam Actual Questions

The questions for PgMP were last updated On Jun 13, 2025

At ValidExamDumps, we consistently monitor updates to the PMI PgMP exam questions by PMI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PMI Program Management Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PMI in their PMI PgMP exam. These outdated questions lead to customers failing their PMI Program Management Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PMI PgMP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

The program manager defines the program objectives, requirements, and develops a high-level road map.

To ensure program alignment with the enterprise strategic plan, the program manager should work with which of the following?

Show Answer Hide Answer
Correct Answer: A

Question No. 3

You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this

scenario?

Show Answer Hide Answer
Correct Answer: B

Question No. 5

A critical program for a company fails to delivers its intended benefits. The CEO and program sponsor are both held accountable and, ultimately, their employment is terminated by the board of directors.

What should the program manager do before formally closing the program?

Show Answer Hide Answer
Correct Answer: C