Free PECB ISO-9001-Lead-Auditor Exam Actual Questions

The questions for ISO-9001-Lead-Auditor were last updated On Jun 13, 2025

At ValidExamDumps, we consistently monitor updates to the PECB ISO-9001-Lead-Auditor exam questions by PECB. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the PECB QMS ISO 9001:2015 Lead Auditor exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by PECB in their PECB ISO-9001-Lead-Auditor exam. These outdated questions lead to customers failing their PECB QMS ISO 9001:2015 Lead Auditor exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the PECB ISO-9001-Lead-Auditor exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

You are conducting a third-party audit to ISO 9001 and interviewing the Training Manager. She explains that training is more

important than ever because the organisation has had to reduce the number of staff employed. Many of the remaining staff

are now required to be 'multi-skilled'. You ask to see plans for the multi-skilling training and are shown plans that look

comprehensive, and include both 'on the job" training and internal and external training courses.

The records indicate that several staff required parts of their training to be repeated one month after the first training was

provided. You ask why this was needed and are told that an investigation of customer complaints identified that several staff

members did not complete certain tasks in the correct manner. The extra training was therefore recommended as a

corrective action.

Based on this interview, which two of the tollowing audit trails would be the most appropriate to follow?

Select the two most appropriate audit trails from the following.

Show Answer Hide Answer
Correct Answer: A, F

When conducting a third-party audit to ISO 9001, especially in the context of training and corrective actions taken due to customer complaints, the most appropriate audit trails to follow would be:

A . Ask if customer complaints had ceased since the multi-skilled training finished. This audit trail is relevant because it directly relates to the effectiveness of the corrective action taken. If customer complaints have decreased or ceased, it could indicate that the additional training was effective1.

F . Review records to assess if all planned training has been completed. This trail is important to ensure that the training plan has been fully implemented and to verify that all staff members have received the necessary training. It also helps in assessing the adequacy of the training in terms of content, frequency, and outcomes1.

These two trails, A and F, are closely linked to the issue of customer complaints and the organization's response to them. They provide insight into whether the actions taken were suitable and whether they have led to improvements in staff performance and customer satisfaction1. The other options, while potentially useful, do not directly address the immediate concern of the effectiveness of the corrective actions taken in response to the customer complaints1.


Question No. 2

Select six tasks you would expect to be completed at the audit team meeting of a third-party audit team leader and his audit team in preparation for a Closing meeting for a four-day initial certification audit.

Show Answer Hide Answer
Correct Answer: C, D, E, F, H, I

The tasks that are expected to be completed at the audit team meeting of a third-party audit team leader and his audit team in preparation for a Closing meeting for a four-day initial certification audit are:

*Option C: Final audit team meeting to agree findings and categories including clarification of any uncertainties. This option is correct because the audit team meeting is an opportunity for the audit team leader and the audit team members to review and consolidate the audit findings, to ensure that they are clear, accurate, objective, and supported by sufficient audit evidence. The audit team should also agree on the categories of the findings, such as nonconformity, observation, or opportunity for improvement, and resolve any uncertainties or disagreements among the audit team members.

*Option D: Agree the roles of each audit team member for the closing meeting. This option is correct because the audit team meeting is an opportunity for the audit team leader to assign the roles and responsibilities of each audit team member for the closing meeting, such as presenting the audit findings, answering questions, or taking notes. The audit team leader should also ensure that the audit team members are prepared and confident to perform their roles and to communicate effectively with the auditee.

*Option E: Audit team review any points raised by the auditee nominated representative. This option is correct because the audit team meeting is an opportunity for the audit team to review any points raised by the auditee nominated representative during the audit, such as requests for clarification, feedback, or complaints. The audit team should consider the validity and relevance of the points raised and decide how to address them in the closing meeting or in the audit report.

*Option F: Audit team agree final audit outcome recommendation. This option is correct because the audit team meeting is an opportunity for the audit team to agree on the final audit outcome recommendation, based on the audit findings and the audit criteria. The audit team should also consider the implications and consequences of the audit outcome recommendation for the auditee and the certification body, and ensure that the recommendation is consistent and justified.

*Option H: Audit team complete final version of their individual findings. This option is correct because the audit team meeting is an opportunity for the audit team to complete the final version of their individual findings, based on the agreement and feedback from the audit team meeting. The audit team should ensure that their individual findings are written in a clear, concise, and factual manner, and that they include the audit criteria, the audit evidence, and the audit conclusion. The audit team should also submit their individual findings to the audit team leader for review and approval.

*Option I: Re-audit corrective actions taken to correct findings found during the audit. This option is correct because the audit team meeting is an opportunity for the audit team to re-audit the corrective actions taken by the auditee to correct the findings found during the audit, if applicable and feasible. The audit team should verify the effectiveness and adequacy of the corrective actions and update the audit findings accordingly. The audit team should also document the results of the re-audit and communicate them to the auditee.

The following options are not correct:

*Option A: Audit team leader informs the individual(s) managing the audit programme that the closing meeting is ready to be held. This option is not correct because this task is not part of the audit team meeting, but part of the communication between the audit team leader and the individual(s) managing the audit programme. The audit team leader should inform the individual(s) managing the audit programme that the closing meeting is ready to be held after the audit team meeting, when the audit team has completed all the tasks and is ready to present the audit results to the auditee.

*Option B: Hold daily audit team meeting to review any timetable issues and potential findings and their impact on the audit for other team members. This option is not correct because this task is not part of the final audit team meeting, but part of the daily audit team meetings that are held during the audit. The daily audit team meetings are opportunities for the audit team to review the progress and performance of the audit, to identify and resolve any issues or problems, and to coordinate and adjust the audit plan and activities as needed.

*Option G: Audit team leader completes final report, including individual findings and certification recommendation. This option is not correct because this task is not part of the audit team meeting, but part of the audit reporting process. The audit team leader should complete the final report, including the individual findings and the certification recommendation, after the closing meeting, when the audit team has received and considered the feedback and comments from the auditee. The audit team leader should also ensure that the final report is reviewed and approved by the appropriate authorities before issuing it to the auditee and the certification body.

*Option J: Write the audit finding report out when detected and obtain signature of the auditee. This option is not correct because this task is not part of the audit team meeting, but part of the audit evidence collection and documentation process. The audit team should write the audit finding report out when detected and obtain the signature of the auditee during the audit, when the audit team has observed and verified the audit evidence and has communicated the audit finding to the auditee. The signature of the auditee does not indicate acceptance or agreement with the audit finding, but only acknowledgement of receipt.


*ISO 19011:2018 Guidelines for auditing management systems, Clause 6.4.2: Conducting audit activities, Subclause i) and j)

*ISO 9001 Lead Auditor Course Material, Module 5: Conducting an Audit, Slide 19: Audit Team Meeting

*ISO 9001 Lead Auditor Training Course - IRCA Certified, Section 5.4: Audit Team Meeting

*Lead Auditor Exam Preparation Guide (EPG) Template - PECB, Section 3.2: Exam Content Outline, Subsection 3.2.1: Section 1 - Audit Fundamentals, Subsection 3.2.2: Section 2 - Audit Principles, Subsection 3.2.3: Section 3 - Audit Process, Subsection 3.2.4: Section 4 - Audit Competencies

Question No. 3

During a second-party audit of a dairy farm (by a potential customer) complying with ISO 9001:2015, the auditor verifies that there is large variability in the daily production of the milking yard. The current agreement with their only customer is to provide 2,000 litres per day. However, in the last two years, they have noticed an increasing variability in daily production.

If they produce less than 2,000 litres, they are penalised with a fine of 1.5 pesos for every litre that they do not provide. If they produce more than 2,000 litres, they use the extra milk to feed the pigs.

This process has been in operation for decades. The dairy farm was founded by the grandfather of the current owners, who did not want to alter the established practices.

The auditor raises a nonconformity on the basis that the process is not under control (Clause 8.1).

If you had been the auditor, which one of the following actions would you have accepted?

Show Answer Hide Answer
Correct Answer: B

The action that the auditor would have accepted is:

*Option B: Apply the existing process of addressing the risks and opportunities of milk production. This option is correct because ISO 9001:2015 clause 8.1 requires the organization to plan, implement and control the processes needed to meet the requirements for the provision of products and services, and to implement actions determined in clause 6.1, which refers to the actions to address risks and opportunities. The organization should apply the existing process of addressing the risks and opportunities of milk production, which may include identifying the sources of variability, assessing the potential impacts and consequences, determining and implementing appropriate actions to reduce or eliminate the variability, monitoring and measuring the effectiveness of the actions, and reviewing and updating the actions as necessary.

The following options are not correct:

*Option A: Modify the contract with the current customer to provide them with only 1,500 litres of milk per day and make an agreement with a second customer. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to meet the customer and applicable statutory and regulatory requirements, as required by ISO 9001:2015 clause 8.2.2.

*Option C: Retain the current contract and try to sell the occasional surplus milk to a second customer. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to meet the customer and applicable statutory and regulatory requirements, as required by ISO 9001:2015 clause 8.2.2.

*Option D: Analyse the daily dispatch of milk for 7 days to determine its variability. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to implement actions to address risks and opportunities, as required by ISO 9001:2015 clause 8.1.


*ISO 9001:2015 Quality management systems - Requirements, Clause 8: Operation, Subclause 8.1: Operational planning and control, Subclause 8.2: Requirements for products and services

*ISO 9001 Lead Auditor Course Material, Module 4: ISO 9001:2015 Requirements, Slide 23: Clause 8 - Operation

*ISO 9001 Lead Auditor Training Course - IRCA Certified, Section 4.2: ISO 9001:2015 Requirements, Subsection 4.2.8: Clause 8 - Operation

*Lead Auditor Exam Preparation Guide (EPG) Template - PECB, Section 3.2: Exam Content Outline, Subsection 3.2.1: Section 1 - Audit Fundamentals, Subsection 3.2.2: Section 2 - Audit Principles, Subsection 3.2.3: Section 3 - Audit Process, Subsection 3.2.4: Section 4 - Audit Competencies

Question No. 4

A small deaning services organisation is about to start work on a hospital dleaning contract for the local Health Trust. You, as auditor, are conducting a Stage 2 audit to ISO 9001 and review the contract with the Service Manager. The contract requires that a cleaning plan is produced. You: "How was the cleaning plan for the contract developed?" Service Manager: "We have a basic template that covers the materials, labour requirements and cleaning methods to be employed. Some of that is specified by the customer." You: "How does the plan deal with locations like the intensive care wards and the operating theatres, which are included in the contract?" Service Manager: "The basic plan covers general wards, but we will do more frequent cleaning in those areas if the hospital requests it." You: "Are you aware of the regulatory requirements for cleaning standards in hospitals?" Service Manager: "No. We depend on the hospital to look after that side of things in the contract." You decide to raise a non-conformity against section 8.2.2.a.1 of ISO 9001. You decide to raise another non-conformity against section 8.2.4 of ISO 9001 when finding that the cleaning plan was amended without the agreement of the Health Trust. A different cleaning chemical was substituted to that specified in the contract. At the follow- up audit, the corrective action proposed was to "obtain a concession from the Health Trust for use of the new chemical." Which one of the following options is the reason why you did not accept this action taken?

Show Answer Hide Answer
Correct Answer: D

Clause 8.2.4 of ISO 9001:2015 -- Changes to Requirements for Products and Services:

ISO 9001:2015 Clause 8.2.4 states that when changes to requirements for products or services are made, they must be communicated and agreed upon with relevant interested parties (in this case, the Health Trust). The lack of communication and agreement for substituting the cleaning chemical represents a clear violation of this clause.

Analysis of the Corrective Action Proposed:

The organization proposed 'obtaining a concession from the Health Trust for the use of the new chemical.' This action is reactive and assumes approval from the Health Trust without addressing the systemic issue: the lack of a defined change control process for managing contract changes.

Option Analysis:

A . The substitute chemical has not been used before in the Health Trust:

Incorrect. While this may be a concern, it is not directly relevant to the root cause of the nonconformity, which is the absence of a process to handle contract changes.

B . The action assumes that the Health Trust will agree to the change:

Incorrect. Although this is true, it is not the primary issue. The nonconformity lies in the lack of a structured approach to obtain agreement, not whether the Health Trust agrees.

C . Staff have not been trained in the use of the new chemical:

Incorrect. This is a separate issue related to staff competence (Clause 7.2), but it is not the main reason why the corrective action is unacceptable under Clause 8.2.4.

D . The process for making changes to the contract has not been addressed:

Correct. The fundamental issue is the organization's failure to follow or establish a change control process for amending contracts, including gaining formal agreement from the Health Trust. The proposed corrective action does not ensure that such issues will be systematically prevented in the future.

E . The substitute chemical may not be as effective as the original:

Incorrect. The effectiveness of the substitute chemical is secondary to the primary issue, which is the lack of a change management process.

ISO 9001 Reference Supporting the Correct Answer:

Clause 8.2.4: Requires that changes to product/service requirements be reviewed, communicated, and agreed upon with the customer.

Clause 10.2 (Nonconformity and Corrective Action): Requires the organization to address the root cause of the nonconformity and take actions to ensure it does not recur. In this case, the root cause is the absence of a change control process.

Why D is the Best Answer:

The core issue is that the organization did not have a formalized process for managing and agreeing upon changes to contract requirements. Addressing this process gap is essential to prevent recurrence of similar nonconformities. Merely seeking a concession from the Health Trust is a one-off solution that does not address the systemic issue.


Question No. 5

Which two of the following work documents are not required for audit planning by an auditor conducting a certification audit?

Show Answer Hide Answer
Correct Answer: A, F