At ValidExamDumps, we consistently monitor updates to the Oracle 1Z0-1057-24 exam questions by Oracle. Whenever our team identifies changes in the exam questions, objectives, focus areas or requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these up to date and 100% exam domain coverage questions, our customers can successfully pass the Oracle Project Management Cloud 2024 Implementation Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by Oracle in their 1Z0-1057-24 exam. These outdated questions lead to customers failing their Oracle Project Management Cloud 2024 Implementation Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions. Our main priority is your success in the Oracle 1Z0-1057-24 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question 1

Your customer has the following setups on the project plan type that they are using for their projects:

Use Task Planned Dates as Task Assignment Dates = Yes

Automatically Roll Up Task Planned Dates = Yes

Synchronize Task Transaction Dates with Planned Dates = No

With these setups in place, you perform the following actions:

1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.

2. Create another new subtask (Sub Task 2) after the previous action is saved.

What would the correct behavior of the application be after these actions? (Choose the best answer.)

Answer Options
Correct Answer: C
Question 2

You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three.)

Answer Options
Correct Answer: A, B, D
Explanation

To allocate the rental cost to the projects and tasks based on the raw costs of the tasks from the previous month, you need to do the following:

Allocate rental costs once each accounting period by using the ''full'' allocation method. This method allocates the entire source amount to the target tasks in one run.

Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period. This ensures that the source amount is proportionally allocated to the tasks based on their relative raw costs.

Define allocation basis by using Actual Amounts with a period-to-date amount class. This allows you to use the actual raw costs of the tasks as the basis for allocation and to use the amounts from the previous accounting period. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2355951

Question 3

Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)

Answer Options
Correct Answer: A
Question 4

A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)

Answer Options
Correct Answer: D
Explanation

Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuration-define-project-resource-breakdown-structures.html#OAPFM180158_2

Why can't I find persons in the list of resources when I enter team members, planning resources, or person rate schedules?

You can't find persons in the list of resources when you enter team members, planning resources, or person rate schedules in the following situations:

The administrator didn't assign a department while creating users. Persons must have an active assignment and be assigned to a department in Oracle Fusion Human Capital Management before they can be added as team members or entered as resources on the planning resource breakdown structure or person rate schedule.

The resource isn't active in Oracle Fusion Human Capital Management because the current date is before the effective date of the resource. If you want to include persons who will start in the future, select the Include people with future-dated effective start dates option when you search for the person.

Persons assigned as project managers aren't active as of the project start date.

The assignment of the person is terminated, and an appropriate value isn't set for the number of days to display people with terminated assignments. You can set the profile value appropriately at the site profile level using the Specify Number of Days to Display People with Terminated Assignments task in the Setup and Maintenance work area.

Question 5

Your customer has separate organizations to maintain indirect, capital, and billing types of projects.

Identify the two setups that can be used to fulfill this requirement. (Choose two.)

Answer Options
Correct Answer: C, D