NCARB Project-Management Practice Exam Questions & Answers

7 Free Questions Last reviewed November 5, 2026 Prepared & Reviewed by the ValidExamDumps Editorial Team

79 Practice Questions (Our Bank)
180 minutes Exam Duration
59-71% of scored items Passing Score
USD 235 Official Exam Fee
Exam Facts

NCARB Project-Management Exam Details

Key details for this exam, checked against the published exam outline

Exam Code
Project-Management
Full Name
ARE 5.0 Project Management (PjM) Exam
Issuing Body
National Council of Architectural Registration Boards (NCARB)
Question Format (Our Bank)
Multiple Choice
Delivery
Computer-based proctored exam
Eligibility
Candidates must establish NCARB record and receive eligibility from their jurisdiction
Practice Questions

Free Project-Management Practice Questions

Each question shows the correct answer and an explanation of why it is right

VA
ValidExamDumps Editorial Team Every question and its answer is checked by our Project-Management exam preparation team, who also write the explanation shown with each one. How we research and review these pages

Question 1 Domain 3 Contracts

An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower. The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.

During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.

What should the architecture firm do first to maintain the start of construction?

Correct Answer A
Explanation

When an owner requests a significant change during the design development phase---such as changing an amenity space from a business center to a private restaurant---this constitutes a change in scope. Such changes often require additional design work, engineering effort, and potentially extended schedules.

The mechanical engineer has indicated the schedule must be extended by four weeks due to this scope change. To maintain project momentum and avoid delays, the architecture firm should first address the issue of compensation for this added scope and extended time. This ensures that the consultants are compensated fairly before additional work proceeds.

Option A is the correct first step: The architect should request the owner to approve an adjustment to compensation reflecting the additional scope and time required.

Option B (approving design loads) is premature before addressing scope and compensation changes.

Option C (receiving owner's written approval of the schedule change) is important but generally follows agreement on compensation and scope adjustment.

Option D (changing the C401 agreement to reflect schedule extension) might be required eventually but the initial and most critical step is securing compensation approval from the owner before contract modifications.

This aligns with standard project management practices and AIA contract guidelines that emphasize properly managing changes in scope, compensation, and schedule to avoid disputes and maintain project control.

Reference from ARE 5.0 Project Management (PjM) division:

AIA Document C401 (Architect-Consultant Agreement) --- managing scope changes, compensation adjustments, and schedule modifications

Project Management best practices for scope, schedule, and compensation control

NCARB ARE 5.0 PjM study materials on change management during design phases

Contract administration guidance on coordinating owner-consultant agreements when scope changes occur

Question 2 Domain 1 Integration of Building Materials & Systems

A new multifamily apartment building is constructed using a construction manager at-risk delivery method. The owner is eager to begin leasing units in the building and requests that the architect sign the certificate of substantial completion without listing any work to be completed.

Which party is required to sign the certificate of substantial completion?

Correct Answer D
Explanation

The AIA A201 and B101 clearly state that the architect is the one who certifies substantial completion. The architect must inspect the work and include a list of incomplete or corrective work (a 'punch list') as part of the Certificate of Substantial Completion.

The building inspector may issue a certificate of occupancy, but the architect is responsible for certifying substantial completion.


AIA A201-2017 9.8.4

AIA G704 Certificate of Substantial Completion

NCARB ARE 5.0 Handbook -- Construction & Closeout Tasks

Question 3 Domain 4 Project Work Planning

Subsequent to the preparation of construction documents, prior to permitting, the enactment of codes or laws requires changes to the project.

Which of the following should occur?

Correct Answer A
Explanation

According to AIA B101, Section 4.2 (Additional Services), changes required by the enactment or revision of codes, laws, or regulations after the preparation of construction documents are considered Additional Services. The architect is entitled to additional compensation for the time and work required to revise the documents accordingly.


AIA B101 -- Article 4.2.3

NCARB ARE 5.0 Handbook -- Architect's services and contractual responsibilities

Get the complete Project-Management question set $20$40

Get Full Access

Question 4 Domain 1 Integration of Building Materials & Systems

Which scheduling method shows the longest path of dependent activities?

Correct Answer B
Explanation

The Critical Path Method (CPM) identifies the longest sequence of dependent tasks that determine the minimum project duration. It highlights critical activities where delays affect the overall schedule. Gantt charts and bar charts are visual scheduling tools but do not calculate critical paths. Flowcharts map processes. CPM is essential in ARE 5.0 PjM for schedule analysis.

Question 5 Domain 5 Resource Management

Refer to the exhibit.

Question 5 exhibit

Prior to the project kick-off, the architect requests to add an additional week of review time to the schedule for each design submission for coordination with their consultants. Based on the schedule provided, what is the earliest start date for construction with the additional review periods?

Correct Answer C
Explanation

There are three phases with design submissions:

SD 30%

DD 60%

CD 90%

Adding 1 extra week for review to each of those phases results in 3 additional weeks total.

Original end of Bidding/Negotiation = October 4 Add 3 weeks = October 25

Coordinating review time with consultants is a best practice and should be reflected in planning deliverables.


AIA Best Practices on project scheduling

Question 6 Domain 2 Project Execution

According to AIA Document A201, who is responsible for obtaining permits and licenses required for the project?

Correct Answer A
Explanation

Per AIA A201 General Conditions, the owner is responsible for obtaining and paying for permits and licenses necessary for the project unless otherwise stated. The contractor typically assists by providing necessary information and submitting documents required by local authorities but the ultimate responsibility lies with the owner. The architect facilitates compliance by producing code-compliant documents but does not directly secure permits. This responsibility division is a key concept in ARE 5.0 PjM relating to roles and obligations defined in contract documents.

Question 7 Domain 2 Project Execution

Which document authorizes the contractor to proceed with work?

Correct Answer A
Explanation

The Notice to Proceed is a formal document issued by the owner or architect authorizing the contractor to begin work on the project and establishing the contract start date. Purchase orders are for procurement; change orders modify contracts; certificates of substantial completion recognize project milestones. ARE 5.0 PjM tests knowledge of construction administration documents.

Study Guide

What the NCARB Project-Management Exam Covers

Exam domains verified against the Official NCARB Project-Management exam guide, last checked November 2026.

Domain 1 Integration of Building Materials & Systems

19% - 25%

Maintain proper Standard of Care through quality control methods and administrative procedures throughout the project. Apply procedures for legal and regulatory adherence, identify quality control steps to reduce risks and liabilities, and perform reviews of project documentation to maintain design integrity.

Sample questions from this domain above Q2Q4

Domain 2 Project Execution

17% - 23%

Manage the project's execution phase through administrative procedures rather than design decisions. Evaluate budget compliance, address scope changes and scope creep, ensure documentation supports the chosen delivery method, and obtain required approvals from authorities having jurisdiction.

Sample questions from this domain above Q6Q7

Domain 3 Contracts

25% - 31%

Analyze the agreements that define relationships among the architect, owner, contractors and consultants. Focus on evaluating adherence to owner-architect agreements, interpreting key elements of architect-consultant and owner-contractor relationships, and integrating consultant work into the overall project.

Sample question from this domain above Q1

Domain 4 Project Work Planning

17% - 23%

Develop and communicate effective work plans with the project team to complete the project on schedule. Establish project schedules, determine communication protocols for owner, contractor, consultants and internal staff, and maintain project documentation throughout delivery.

Sample question from this domain above Q3

Domain 5 Resource Management

7% - 13%

Determine the composition of the project team and how each member's time will be managed and allocated to execute the project. Establish criteria for assembling the team, assess requirements for allocating and managing project resources effectively throughout the engagement.

Sample question from this domain above Q5

FAQ

Project-Management Exam FAQ

Common questions about the exam itself

What background do I need before taking the Project Management exam?
You need an NCARB record and eligibility approval from your state or local licensing board. Requirements vary by jurisdiction, so check your board's specific rules before applying. Once approved, you can schedule the exam.
How hard is the Project Management exam compared to other ARE 5.0 divisions?
Project Management has a 60% pass rate, making it moderately difficult. It tests practical skills in contract interpretation, budget management and team coordination rather than technical design knowledge, which some candidates find more straightforward than the technical divisions.
How long should I prepare for Project Management?
Most candidates spend 4 to 8 weeks preparing, though this depends on your experience with project administration. If you have worked in an architectural office managing projects or consultants, you may need less time. NCARB offers a free full-length practice exam in your Record.
What is the most challenging section of Project Management?
Contracts is the largest section at 25-31% of the exam and requires detailed understanding of architect-owner, architect-consultant and owner-contractor agreements. Many candidates struggle with interpreting specific contractual obligations and recognizing when terms are violated.
What happens on exam day for Project Management?
You have 3 hours to answer 75 questions in a computer-based proctored format. The exam includes case studies with supporting project documents you must review to answer related questions. An on-screen calculator and code references are provided, but you cannot bring external materials.
Can I retake Project Management if I fail?
Yes. You can retake any division, and each attempt costs USD 235. You can reschedule an existing appointment up to 24 hours before an online exam or 48 hours before an in-person exam at a test centre.
How long is my Project Management certification valid?
A passed exam remains valid for the version in which you took it, plus one additional version as NCARB releases updates. This means your passing score does not expire immediately but will not carry forward indefinitely as new exam versions roll out.
Which job role does Project Management prepare me for?
Project Management certification demonstrates competency for roles such as Project Manager, Project Architect or Senior Architect managing day-to-day project delivery, budget, consultants and quality control in an architectural practice.
How does Project Management relate to Practice Management on the ARE 5.0?
Practice Management (PcM) focuses on running the entire architectural firm while Project Management (PjM) focuses on delivering individual projects. Many candidates take PcM first, then PjM, since you must understand firm-wide practice before managing projects.

Other NCARB Exams

Free practice questions for more NCARB certification exams

All NCARB exams