NCARB Project-Management Practice Exam Questions & Answers
NCARB Project-Management Exam Details
Key details for this exam, checked against the published exam outline
- Exam Code
- Project-Management
- Full Name
- ARE 5.0 Project Management (PjM) Exam
- Issuing Body
- National Council of Architectural Registration Boards (NCARB)
- Question Format (Our Bank)
- Multiple Choice
- Delivery
- Computer-based proctored exam
- Eligibility
- Candidates must establish NCARB record and receive eligibility from their jurisdiction
- Full Question Set
- 79 questions Get All Questions
Free Project-Management Practice Questions
Each question shows the correct answer and an explanation of why it is right
Question 1 Domain 3 Contracts
An architecture firm has a C401 agreement with their consultants for a new design-bid-build residential tower. The architect has approved a schedule provided by the mechanical engineer that includes a two-week quality control review after each delivery milestone.
During the design development phase, the owner requests that the architect change the 8,000-square-foot business center amenity for tenants to a private restaurant. The mechanical engineer informs the architect that their schedule must be extended by four weeks to meet the owner's request.
What should the architecture firm do first to maintain the start of construction?
When an owner requests a significant change during the design development phase---such as changing an amenity space from a business center to a private restaurant---this constitutes a change in scope. Such changes often require additional design work, engineering effort, and potentially extended schedules.
The mechanical engineer has indicated the schedule must be extended by four weeks due to this scope change. To maintain project momentum and avoid delays, the architecture firm should first address the issue of compensation for this added scope and extended time. This ensures that the consultants are compensated fairly before additional work proceeds.
Option A is the correct first step: The architect should request the owner to approve an adjustment to compensation reflecting the additional scope and time required.
Option B (approving design loads) is premature before addressing scope and compensation changes.
Option C (receiving owner's written approval of the schedule change) is important but generally follows agreement on compensation and scope adjustment.
Option D (changing the C401 agreement to reflect schedule extension) might be required eventually but the initial and most critical step is securing compensation approval from the owner before contract modifications.
This aligns with standard project management practices and AIA contract guidelines that emphasize properly managing changes in scope, compensation, and schedule to avoid disputes and maintain project control.
Reference from ARE 5.0 Project Management (PjM) division:
AIA Document C401 (Architect-Consultant Agreement) --- managing scope changes, compensation adjustments, and schedule modifications
Project Management best practices for scope, schedule, and compensation control
NCARB ARE 5.0 PjM study materials on change management during design phases
Contract administration guidance on coordinating owner-consultant agreements when scope changes occur
Question 2 Domain 1 Integration of Building Materials & Systems
A new multifamily apartment building is constructed using a construction manager at-risk delivery method. The owner is eager to begin leasing units in the building and requests that the architect sign the certificate of substantial completion without listing any work to be completed.
Which party is required to sign the certificate of substantial completion?
The AIA A201 and B101 clearly state that the architect is the one who certifies substantial completion. The architect must inspect the work and include a list of incomplete or corrective work (a 'punch list') as part of the Certificate of Substantial Completion.
The building inspector may issue a certificate of occupancy, but the architect is responsible for certifying substantial completion.
AIA A201-2017 9.8.4
AIA G704 Certificate of Substantial Completion
NCARB ARE 5.0 Handbook -- Construction & Closeout Tasks
Question 3 Domain 4 Project Work Planning
Subsequent to the preparation of construction documents, prior to permitting, the enactment of codes or laws requires changes to the project.
Which of the following should occur?
According to AIA B101, Section 4.2 (Additional Services), changes required by the enactment or revision of codes, laws, or regulations after the preparation of construction documents are considered Additional Services. The architect is entitled to additional compensation for the time and work required to revise the documents accordingly.
AIA B101 -- Article 4.2.3
NCARB ARE 5.0 Handbook -- Architect's services and contractual responsibilities
Get the complete Project-Management question set
$20$40
Question 4 Domain 1 Integration of Building Materials & Systems
Which scheduling method shows the longest path of dependent activities?
The Critical Path Method (CPM) identifies the longest sequence of dependent tasks that determine the minimum project duration. It highlights critical activities where delays affect the overall schedule. Gantt charts and bar charts are visual scheduling tools but do not calculate critical paths. Flowcharts map processes. CPM is essential in ARE 5.0 PjM for schedule analysis.
Question 5 Domain 5 Resource Management
Refer to the exhibit.

Prior to the project kick-off, the architect requests to add an additional week of review time to the schedule for each design submission for coordination with their consultants. Based on the schedule provided, what is the earliest start date for construction with the additional review periods?
There are three phases with design submissions:
SD 30%
DD 60%
CD 90%
Adding 1 extra week for review to each of those phases results in 3 additional weeks total.
Original end of Bidding/Negotiation = October 4 Add 3 weeks = October 25
Coordinating review time with consultants is a best practice and should be reflected in planning deliverables.
AIA Best Practices on project scheduling
Question 6 Domain 2 Project Execution
According to AIA Document A201, who is responsible for obtaining permits and licenses required for the project?
Per AIA A201 General Conditions, the owner is responsible for obtaining and paying for permits and licenses necessary for the project unless otherwise stated. The contractor typically assists by providing necessary information and submitting documents required by local authorities but the ultimate responsibility lies with the owner. The architect facilitates compliance by producing code-compliant documents but does not directly secure permits. This responsibility division is a key concept in ARE 5.0 PjM relating to roles and obligations defined in contract documents.
Question 7 Domain 2 Project Execution
Which document authorizes the contractor to proceed with work?
The Notice to Proceed is a formal document issued by the owner or architect authorizing the contractor to begin work on the project and establishing the contract start date. Purchase orders are for procurement; change orders modify contracts; certificates of substantial completion recognize project milestones. ARE 5.0 PjM tests knowledge of construction administration documents.
What the NCARB Project-Management Exam Covers
Exam domains verified against the Official NCARB Project-Management exam guide, last checked November 2026.
Domain 1 Integration of Building Materials & Systems
19% - 25%Maintain proper Standard of Care through quality control methods and administrative procedures throughout the project. Apply procedures for legal and regulatory adherence, identify quality control steps to reduce risks and liabilities, and perform reviews of project documentation to maintain design integrity.
Domain 2 Project Execution
17% - 23%Manage the project's execution phase through administrative procedures rather than design decisions. Evaluate budget compliance, address scope changes and scope creep, ensure documentation supports the chosen delivery method, and obtain required approvals from authorities having jurisdiction.
Domain 3 Contracts
25% - 31%Analyze the agreements that define relationships among the architect, owner, contractors and consultants. Focus on evaluating adherence to owner-architect agreements, interpreting key elements of architect-consultant and owner-contractor relationships, and integrating consultant work into the overall project.
Sample question from this domain above Q1
Domain 4 Project Work Planning
17% - 23%Develop and communicate effective work plans with the project team to complete the project on schedule. Establish project schedules, determine communication protocols for owner, contractor, consultants and internal staff, and maintain project documentation throughout delivery.
Sample question from this domain above Q3
Domain 5 Resource Management
7% - 13%Determine the composition of the project team and how each member's time will be managed and allocated to execute the project. Establish criteria for assembling the team, assess requirements for allocating and managing project resources effectively throughout the engagement.
Sample question from this domain above Q5
Project-Management Exam FAQ
Common questions about the exam itself
What background do I need before taking the Project Management exam?
How hard is the Project Management exam compared to other ARE 5.0 divisions?
How long should I prepare for Project Management?
What is the most challenging section of Project Management?
What happens on exam day for Project Management?
Can I retake Project Management if I fail?
How long is my Project Management certification valid?
Which job role does Project Management prepare me for?
How does Project Management relate to Practice Management on the ARE 5.0?
Other NCARB Exams
Free practice questions for more NCARB certification exams
