NCARB Project-Management Practice Exam Questions & Answers

5 Free Questions · Last reviewed: September 20, 2026 · Prepared & Reviewed by the ValidExamDumps Editorial Team

Exam Facts

NCARB Project-Management Exam Details

Key details for this exam, checked against the published exam outline

79 Practice Questions (Our Bank)
180 minutes Exam Duration
59-71% of scored items Passing Score
USD 235 Exam Fee
Exam Code
Project-Management
Full Name
ARE 5.0 Project Management (PjM) Exam
Issuing Body
National Council of Architectural Registration Boards (NCARB)
Question Format (Our Bank)
Multiple Choice
Delivery
Computer-based proctored exam
Eligibility
Candidates must establish NCARB record and receive eligibility from their jurisdiction
Practice Questions

Free Project-Management Practice Questions

Each question shows the correct answer and an explanation of why it is right

VA
ValidExamDumps Editorial Team Every question and its answer is checked by our Project-Management exam preparation team, who also write the explanation shown with each one. How we research and review these pages

A construction project is one week away from the date of substantial completion as defined by an AIA A201 agreement. The owner comes forward with a major change to the work. The contractor and owner disagree on how much to extend the contract time. The project needs to proceed without delay while the contractor and owner work out the difference.

Which one of the following steps should the architect take?

Correct Answer: A
Explanation

When there is a disagreement over cost or time but the work must proceed, the architect can issue a Construction Change Directive (CCD). This allows the work to move forward while the owner and contractor negotiate terms. A Minor Change (B) is only for non-cost/time changes. Waiver of Subrogation (C) pertains to insurance.

CCDs are used under AIA A201 7.3 when immediate work is needed but consensus hasn't been reached.

This is the formal process to avoid delay in project delivery.


NCARB ARE 5.0 Handbook -- PjM Content Area 5

What is the architect's responsibility regarding code compliance during design?

Correct Answer: B
Explanation

The architect is responsible for preparing design documents that comply with applicable codes and regulations. Structural design is typically performed by engineers. Permitting and inspections are government responsibilities. Ensuring documents meet code requirements reduces the risk of delays or rework. ARE 5.0 PjM tests understanding of code compliance roles.

During the predesign phase of a project, the architect discovers that the owner's budget is insufficient to meet the program requirements.

Which of the following should the architect do?

Correct Answer: C
Explanation

Comprehensive Detailed Explanation:

During the predesign or programming phase, it is the architect's responsibility to advise the owner when the scope and budget are misaligned. The correct professional approach is to notify the owner that the program cannot be met within the current budget. Solutions (phasing or budget increase) may be discussed after this acknowledgment. The architect should not unilaterally scale down the program without owner input.


NCARB ARE 5.0 Handbook -- Budget evaluation in Programming/Predesign

Refer to the exhibit.

Refer to the exhibit

Twenty-five acres of undeveloped rural property was purchased for the site of a new elementary school. During the DD phase, the civil engineer and structural engineers make design proposals based on the information provided in the geotechnical report. The civil engineer indicates that several cubic yards of fill material should be installed within the proposed building footprint to make up for the change in topography (was uniformly). The structural engineer indicates a footing depth of 24 inches for the entire facility. During the CD phase, the owner asks the architect to add classrooms to one wing. The civil engineer proposes that extra fill should not be installed beneath the additional classrooms.

Which of the following should the architect do before completion of CDs? Check the three that apply.

Correct Answer: A, C, D
Explanation

A . Update the estimate of the cost of work

Adding classrooms affects scope and site preparation (e.g., fill material, grading, foundations), which affects cost. Per AIA B101 6.3, architects must update the estimate of the cost of the work as the design evolves.

C . Request an updated geotechnical evaluation

The original geotech report didn't account for this building extension. Without fill under the new addition, soil bearing capacity must be reassessed to avoid differential settlement or structural failure. This is a standard risk mitigation strategy.

D . Notify the structural engineer of the civil engineer's recommendation

The structural engineer must know that the site prep differs under the added classrooms, as this could affect foundation design. Coordination among consultants is a core architectural responsibility (per B101 3.1.2).

Incorrect Options:

B . Schedule a quality assurance meeting with the project team

While helpful, it's not critical or required specifically in this context before CDs are completed.

E . Increase the footing depth beneath the new classrooms

The architect should not unilaterally change structural design decisions. That's the structural engineer's responsibility, and any change should be based on engineering analysis and revised soil data.

F . Add general notes about structural bearing to the drawings

Premature. The structural engineer should first review the new geotechnical findings before any notes are added.


AIA B101 -- Article 3.1 & 3.2 (Architect's coordination & design responsibilities)

NCARB ARE 5.0 Handbook -- PjM Content Area 1: Project Coordination

Geotechnical coordination practices, CSI Spec Guidelines

A key Project Manager leaves an architectural firm halfway through a project. Several days of lost productivity pass while the new Project Manager determines the customized organization that the previous Project Manager used. The new Project Manager recommends implementing new office policies to create standards and quality control methods for the entire office.

Which methods should be implemented? Check the four that apply.

Correct Answer: A, B, D, E
Explanation

Comprehensive Detailed Explanation:

Best practices in quality management include:

A . Reviewing existing methods to identify inefficiencies

B . Standardizing workflow to prevent variability and loss of knowledge

D . Measuring performance to track productivity and outcomes

E . Continuous improvement ensures the office adapts and grows

C is incorrect as customization contradicts standardization and is the root of the issue. F is a drastic step not warranted by the situation.


NCARB ARE 5.0 PjM Handbook -- Quality management and office standards

Ballast ARE 5 Review Manual -- Project Management tools and quality assurance

AIA Best Practices -- Office workflow documentation and training

Get Full Access

79 questions covering all exam domains

Study Guide

What the NCARB Project-Management Exam Covers

Exam domains verified against: Official NCARB Project-Management exam guide, last checked September 2026.

Domain 1: Contracts 25% - 31%

Analyze the agreements that define relationships among the architect, owner, contractors and consultants. Focus on evaluating adherence to owner-architect agreements, interpreting key elements of architect-consultant and owner-contractor relationships, and integrating consultant work into the overall project.

Sample questions from this domain above: Q1Q3

Domain 2: Project Work Planning 17% - 23%

Develop and communicate effective work plans with the project team to complete the project on schedule. Establish project schedules, determine communication protocols for owner, contractor, consultants and internal staff, and maintain project documentation throughout delivery.

Sample question from this domain above: Q5

Domain 3: Project Execution 17% - 23%

Manage the project's execution phase through administrative procedures rather than design decisions. Evaluate budget compliance, address scope changes and scope creep, ensure documentation supports the chosen delivery method, and obtain required approvals from authorities having jurisdiction.

Domain 4: Integration of Building Materials & Systems 19% - 25%

Maintain proper Standard of Care through quality control methods and administrative procedures throughout the project. Apply procedures for legal and regulatory adherence, identify quality control steps to reduce risks and liabilities, and perform reviews of project documentation to maintain design integrity.

Sample question from this domain above: Q4

Domain 5: Resource Management 7% - 13%

Determine the composition of the project team and how each member's time will be managed and allocated to execute the project. Establish criteria for assembling the team, assess requirements for allocating and managing project resources effectively throughout the engagement.

Sample question from this domain above: Q2

FAQ

Project-Management Exam FAQ

Common questions about the exam itself

What background do I need before taking the Project Management exam?
You need an NCARB record and eligibility approval from your state or local licensing board. Requirements vary by jurisdiction, so check your board's specific rules before applying. Once approved, you can schedule the exam.
How hard is the Project Management exam compared to other ARE 5.0 divisions?
Project Management has a 60% pass rate, making it moderately difficult. It tests practical skills in contract interpretation, budget management and team coordination rather than technical design knowledge, which some candidates find more straightforward than the technical divisions.
How long should I prepare for Project Management?
Most candidates spend 4 to 8 weeks preparing, though this depends on your experience with project administration. If you have worked in an architectural office managing projects or consultants, you may need less time. NCARB offers a free full-length practice exam in your Record.
What is the most challenging section of Project Management?
Contracts is the largest section at 25-31% of the exam and requires detailed understanding of architect-owner, architect-consultant and owner-contractor agreements. Many candidates struggle with interpreting specific contractual obligations and recognizing when terms are violated.
What happens on exam day for Project Management?
You have 3 hours to answer 75 questions in a computer-based proctored format. The exam includes case studies with supporting project documents you must review to answer related questions. An on-screen calculator and code references are provided, but you cannot bring external materials.
Can I retake Project Management if I fail?
Yes. You can retake any division, and each attempt costs USD 235. You can reschedule an existing appointment up to 24 hours before an online exam or 48 hours before an in-person exam at a test centre.
How long is my Project Management certification valid?
A passed exam remains valid for the version in which you took it, plus one additional version as NCARB releases updates. This means your passing score does not expire immediately but will not carry forward indefinitely as new exam versions roll out.
Which job role does Project Management prepare me for?
Project Management certification demonstrates competency for roles such as Project Manager, Project Architect or Senior Architect managing day-to-day project delivery, budget, consultants and quality control in an architectural practice.
How does Project Management relate to Practice Management on the ARE 5.0?
Practice Management (PcM) focuses on running the entire architectural firm while Project Management (PjM) focuses on delivering individual projects. Many candidates take PcM first, then PjM, since you must understand firm-wide practice before managing projects.