Free NCARB PDD Exam Actual Questions

The questions for PDD were last updated On Dec 15, 2025

At ValidExamDumps, we consistently monitor updates to the NCARB PDD exam questions by NCARB. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the NCARB ARE 5.0 Project Development and Documentation Exam exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by NCARB in their NCARB PDD exam. These outdated questions lead to customers failing their NCARB ARE 5.0 Project Development and Documentation Exam exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the NCARB PDD exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Which of the following documents would the architect need in order to prepare the specifications?

Show Answer Hide Answer
Correct Answer: C

To prepare project specifications, the architect requires documents that inform about site conditions, building construction, and interior finishes:

Geotechnical report provides soil conditions, foundation recommendations, and site constraints.

Building sections provide detailed information on assemblies, materials, and vertical relationships.

Room finish schedule identifies finishes, materials, and related specifications for interior spaces.

Legal surveys, traffic management plans, and door schedules are important for planning and design coordination but less directly informative for writing specifications.


NCARB ARE 5.0 Review Manual, Project Development and Documentation chapter

CSI Construction Specifications Practice guides

Project delivery and documentation best practices

Question No. 2

Refer to the exhibit.

Refer to the exhibit.

The construction method shown in the detail should be used to prevent cracking in which of the following situations?

Show Answer Hide Answer
Correct Answer: B

The detail shows a steel runner with sheetrock and screws, typical for drywall suspended ceiling assemblies.

This construction method is commonly used in concrete frame buildings with drywall ceilings suspended below the structural slab.

It helps prevent cracking by accommodating building movement and separating finish materials from structural movement.

Structural steel frame buildings with plaster ceilings typically have different finish and framing details.

Concrete flat slabs with exposed ceilings have no finish requiring such assemblies.

Exposed steel frames without partitions don't need drywall framing.


NCARB ARE 5.0 Review Manual, Materials and Assemblies chapter

Interior finishes and drywall system installation guides (Gypsum Association)

Question No. 3

In which of the following locations in concrete masonry should a control joint be placed?

Show Answer Hide Answer
Correct Answer: C

Control joints in concrete masonry walls are designed to accommodate movement caused by thermal expansion, moisture changes, and settlement.

Control joints should be placed at locations of stress concentration, such as changes in wall height, changes in wall thickness, or at large wall expanses.

They are not placed at the first course of masonry (which is typically reinforced and anchored to the foundation).

They are generally not placed at window corners or in the center of window openings but rather at planned intervals or changes in geometry.

Placing a control joint at changes in wall height allows movement without cracking.


NCARB ARE 5.0 Review Manual, Materials and Assemblies chapter

Masonry design and control joint placement per ASTM standards

Masonry construction manuals (e.g., NCMA TEK)

Question No. 4

Which system would most impact the structural loads in a vegetated roof design?

Show Answer Hide Answer
Correct Answer: C

Green roofing adds significant dead loads due to soil and water retention layers. Structural engineers must verify load-bearing capacity. This is tied to ARE Objective 3.2 on evaluating integration of building systems.


Question No. 5

Refer to the exhibit.

Refer to the exhibit.

The exterior cast-in-place concrete wall of a heated building is insulated with polyurethane slabs.

The concrete will be warmest in the winter if the insulation is applied as shown in which of the following?

Show Answer Hide Answer
Correct Answer: D

To keep the concrete warmest in winter, place the continuous insulation on the exterior so the concrete mass stays inside the thermal envelope and sees interior temperatures. This reduces heat loss, limits risk of interstitial condensation at the concrete surface, and improves thermal lag. Option D shows all polyurethane insulation on the outside of the wall; A and B place some or all insulation inside, and C splits it---both allow more winter heat loss from the concrete.

PDD references: Building envelope heat flow & thermal mass strategy; continuous insulation placement (ASHRAE Fundamentals; NCARB ARE 5.0 PDD---Envelope & Thermal/Moisture Protection, CSI Div 07).