Free Hitachi Vantara HQT-4420 Exam Actual Questions

The questions for HQT-4420 were last updated On Jun 12, 2025

At ValidExamDumps, we consistently monitor updates to the Hitachi Vantara HQT-4420 exam questions by Hitachi Vantara. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the Hitachi Vantara Qualified Professional - Content Platform Installation exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by Hitachi Vantara in their Hitachi Vantara HQT-4420 exam. These outdated questions lead to customers failing their Hitachi Vantara Qualified Professional - Content Platform Installation exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the Hitachi Vantara HQT-4420 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

You are preparing to perform an offline upgrade on an HCP G10 and the pre-upgrade check procedure fails. The error message says that you do not have enough capacity on node 103 to perform the upgrade.

Which service procedure should you run to resolve this problem?

Show Answer Hide Answer
Correct Answer: B

If the pre-upgrade check procedure fails due to insufficient capacity on node 103 to perform the upgrade, the service procedure to run is Free Space On Nodes. This procedure helps to identify and clear unnecessary files or redistribute data, freeing up the required capacity on the node to proceed with the upgrade.

Hitachi Vantara Content Platform Installation Reference:

The 'Free Space On Nodes' procedure is specifically designed to manage and optimize storage capacity across HCP nodes, ensuring that upgrades and other operations have adequate space to execute successfully.


Question No. 2

You are performing an online upgrade of an HCP G10 and the upgrade fails.

Which log is available to assist troubleshooting?

Show Answer Hide Answer
Correct Answer: D

When performing an online upgrade of an HCP G10 and the upgrade fails, the Arc-deploy logs are the relevant logs available to assist with troubleshooting. These logs contain detailed information about the deployment and upgrade processes, including errors or issues encountered during the upgrade. Accessing these logs allows administrators to diagnose the failure and take corrective actions.

Hitachi Vantara Content Platform Installation Reference:

The Arc-deploy logs are essential for understanding the sequence of events and identifying the exact step or component that caused the failure during an online upgrade of the HCP G10.


Question No. 3

What is the minimum RAM capacity installed in a HCP G10 server?

Show Answer Hide Answer
Correct Answer: C

The minimum RAM capacity installed in an HCP G10 server is 64 GB. This amount of memory is required to handle the workload associated with managing large datasets, metadata operations, indexing, data deduplication, and compression processes, all of which are essential functions of the HCP platform. The 'HCP Hardware Specification Guide' outlines the minimum hardware requirements necessary to ensure optimal performance and scalability of the platform.


Question No. 4

Which traffic type is allowed on the HCP back-end network?

Show Answer Hide Answer
Correct Answer: C

The HCP back-end network is specifically designed to handle internal cluster traffic such as inter-node communication. This traffic type is critical for maintaining cluster synchronization, managing metadata, balancing loads, and ensuring consistent data storage and retrieval across the nodes in the cluster. Other types of traffic, like BMC access (A), tenant management console access (B), and replication traffic (D), typically occur over separate management or front-end networks. The 'HCP Network Configuration and Management Guide' provides detailed information on network segmentation and the roles of different network types in an HCP environment.


Question No. 5

You are installing an HCP G10 and need to connect to the node using PuTTY after you have installed the OS.

What is used to forward the SSH keys?

Show Answer Hide Answer
Correct Answer: D

Pageant is a PuTTY authentication agent that is used to manage SSH keys for public-key authentication. When installing an HCP G10 and needing to connect to the node using PuTTY after installing the OS, Pageant can be used to forward SSH keys, allowing for a more secure and efficient connection without requiring manual password entry each time. Pageant stores the private keys and forwards them to the SSH client when required.

Hitachi Vantara Content Platform Installation Reference:

Pageant is specifically used in environments where SSH key management is necessary, particularly in secure installations of HCP systems where multiple nodes or connections are being managed.