At ValidExamDumps, we consistently monitor updates to the Exin CDCS exam questions by Exin. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the Exin EXIN EPI Certified Data Centre Specialist exam on their first attempt without needing additional materials or study guides.
Other certification materials providers often include outdated or removed questions by Exin in their Exin CDCS exam. These outdated questions lead to customers failing their Exin EXIN EPI Certified Data Centre Specialist exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the Exin CDCS exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.
What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?
In seismic-prone areas, cables should be tightly secured to racks and cable trays to minimize movement during seismic activity. Properly securing the cables prevents them from being damaged due to excessive motion, which could lead to outages or damage to connected equipment.
Detailed Explanation:
Loose cables can be vulnerable to shaking or sudden jolts during an earthquake, increasing the risk of disconnection or damage. By tightly organizing and securing cables, you ensure they remain in place, even during significant movement, thereby maintaining connection integrity and reducing the risk of physical damage.
EPI Data Center Specialist References:
EPI training includes considerations for data centers in seismic zones, advising that cables be firmly anchored to support structures to reduce movement and mitigate potential damage during seismic events.
Three data centers are benchmarked on facilities energy efficiency.
Data center A has achieved a PUE of 2.45.
Data center B has achieved a PUE of 1.20.
Data center C has achieved a PUE of 1.90.
Which of the data centers is operating at the highest facility efficiency?
A Power Usage Effectiveness (PUE) of 1.20 (achieved by Data Center B) indicates the highest facility efficiency among the three data centers. A lower PUE value signifies better energy efficiency, as it means that a greater proportion of the total energy consumed is used directly for IT equipment rather than for cooling, lighting, or other facility needs.
Detailed Explanation:
PUE is calculated as the ratio of total facility energy to IT equipment energy. A PUE close to 1.0 suggests that almost all the energy is dedicated to computing processes, with minimal overhead. With PUE values of 2.45, 1.20, and 1.90, Data Center B (1.20) operates most efficiently by devoting a higher percentage of its total energy to IT equipment.
EPI Data Center Specialist References:
The EPI curriculum emphasizes PUE as a key metric for data center efficiency, with lower values representing better performance. Achieving a PUE near 1.0 aligns with industry best practices for energy-efficient data center design and operation.
You are allowed to use a calculator for this question. The total power consumption of the ICT equipment in a rack is 6 kW. The equipment is traditional ICT equipment with a Delta-T of approximately 11 C / 20 F. Calculate the approximate CFM required to cool the equipment in the rack.
To calculate the cooling airflow requirement for ICT equipment, you can use the formula:
CFM=Power(kW)3160T(F)\text{CFM} = \frac{\text{Power (kW)} \times 3160}{\Delta T (\text{F})}CFM=T(F)Power(kW)3160
For equipment consuming 6 kW with a Delta-T of 20F:
CFM=6316020=9481,000CFM\text{CFM} = \frac{6 \times 3160}{20} = 948 \approx 1,000 \, \text{CFM}CFM=2063160=9481,000CFM
Detailed Explanation:
This formula provides an estimate of the cubic feet per minute (CFM) of air required to cool the equipment based on its power consumption and the temperature difference (Delta-T) between intake and exhaust. The Delta-T represents the cooling effectiveness of the airflow.
EPI Data Center Specialist References:
EPI recommends using this calculation for determining airflow requirements in data centers, ensuring that cooling systems are adequately sized to maintain equipment within safe temperature limits.
What mainly affects the cooling capacity of a raised floor tile?
The cooling capacity of a raised floor tile is primarily influenced by the percentage of surface opening, the obstruction caused by the supporting construction, the pressure under the raised floor, and the damper construction. These factors dictate how much airflow can pass through the tile and how effectively cool air is distributed to the equipment in the data center.
Detailed Explanation:
The percentage of surface opening on a floor tile affects how much air can flow through, with larger openings allowing more airflow. Supporting structures beneath the floor can obstruct airflow, reducing cooling efficiency. Pressure under the raised floor impacts the velocity and volume of air that moves through the tile. Additionally, if dampers are installed, they control the airflow rate, which can be adjusted to meet specific cooling needs for the area.
EPI Data Center Specialist References:
EPI guidance on airflow management under raised floors emphasizes these factors as critical for effective cooling, especially in high-density areas. Ensuring unobstructed and adequate airflow helps maintain consistent cooling across equipment.
In which stage of the data center life cycle does commissioning take place?
Commissioning occurs during the Implementation stage of the data center life cycle. This phase involves the final testing and verification of systems and equipment to ensure they meet design specifications and operational requirements before the data center goes live.
Detailed Explanation:
The Implement phase includes activities such as installation, configuration, and testing. Commissioning is a crucial step that validates the performance and reliability of all critical systems, including power, cooling, and network infrastructure, to ensure they operate as intended under various conditions. Proper commissioning helps identify and resolve any issues before the data center becomes fully operational.
EPI Data Center Specialist References:
EPI training emphasizes that commissioning is essential for verifying that the data center meets design and performance criteria, aligning with best practices in data center project management to minimize risks and ensure readiness for operation.