Free CompTIA PK0-005 Exam Actual Questions

The questions for PK0-005 were last updated On Jun 13, 2025

At ValidExamDumps, we consistently monitor updates to the CompTIA PK0-005 exam questions by CompTIA. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the CompTIA Project+ Certification Exam exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by CompTIA in their CompTIA PK0-005 exam. These outdated questions lead to customers failing their CompTIA Project+ Certification Exam exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the CompTIA PK0-005 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

Show Answer Hide Answer
Correct Answer: C

Question No. 3

A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

Show Answer Hide Answer
Correct Answer: D

Question No. 4

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

Show Answer Hide Answer
Correct Answer: D

Question No. 5

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

Show Answer Hide Answer
Correct Answer: A