Free BICSI RCDDv14 Exam Actual Questions

The questions for RCDDv14 were last updated On Jun 16, 2025

At ValidExamDumps, we consistently monitor updates to the BICSI RCDDv14 exam questions by BICSI. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the BICSI Registered Communications Distribution Designer (RCDD) exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by BICSI in their BICSI RCDDv14 exam. These outdated questions lead to customers failing their BICSI Registered Communications Distribution Designer (RCDD) exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the BICSI RCDDv14 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

Show Answer Hide Answer
Correct Answer: B, C

Question No. 2

An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

Show Answer Hide Answer
Correct Answer: B

Question No. 3

To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.

What should the program manager do?

Show Answer Hide Answer
Correct Answer: B

Question No. 4

An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building C. Both ends are terminated with SC connectors. What is the loss budget for the above fiber link?

Show Answer Hide Answer
Correct Answer: C

Question No. 5

What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)

Show Answer Hide Answer
Correct Answer: B, E