Free BCS ISEB-PM1 Exam Actual Questions

The questions for ISEB-PM1 were last updated On Dec 14, 2025

At ValidExamDumps, we consistently monitor updates to the BCS ISEB-PM1 exam questions by BCS. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the BCS Foundation Certificate in IS Project Management exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by BCS in their BCS ISEB-PM1 exam. These outdated questions lead to customers failing their BCS Foundation Certificate in IS Project Management exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the BCS ISEB-PM1 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

Show Answer Hide Answer
Correct Answer: C

Question No. 2

In which of the following types of contracts is it most important for the contractor to maintain control of cost, schedule and scope changes.

Show Answer Hide Answer
Correct Answer: C

Question No. 3

In the three-point estimating technique, if the most likely estimate for an activity to complete is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days, what is the expected duration in which the activity will be completed?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

While preparing your risk responses, you realize that you have not planned for unknown risk events. You need to make adjustments to the project to compensate for unknown risk events. These adjustments are based on your past project experience when unknown risk events occurred and knocked the project off track. What should you do?

Show Answer Hide Answer
Correct Answer: A

Question No. 5

Define Activities and Estimate Activity Resources are processes in which project management knowledge area?

Show Answer Hide Answer
Correct Answer: A