Free ASTQB CTFL Exam Actual Questions

The questions for CTFL were last updated On Apr 28, 2025

At ValidExamDumps, we consistently monitor updates to the ASTQB CTFL exam questions by ASTQB. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the ASTQB ISTQB Foundation Level exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by ASTQB in their ASTQB CTFL exam. These outdated questions lead to customers failing their ASTQB ISTQB Foundation Level exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the ASTQB CTFL exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

What are the key features to be concentrated upon when doing a testing forworld wide web sites ..?

Show Answer Hide Answer
Correct Answer: D

Question No. 2

Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management. 1 credit

Show Answer Hide Answer
Correct Answer: A, B

Question No. 3

Which of the following is MOST important in the selection of a test approach?

Show Answer Hide Answer
Correct Answer: C

Question No. 4

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a. Any deviation from the procedures described in the test

b. strategy document

c. The overall estimated costs, timescales and resource

d. requirements

e. A detailed schedule of testing activities

f. The development deliverables to be tested

g. Which test staff members (names) will be involved and when

h. Level of requirements coverage achieved

Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit

Show Answer Hide Answer
Correct Answer: C, E

Question No. 5

What is important to do when working with software development models?

Show Answer Hide Answer
Correct Answer: A