At ValidExamDumps, we consistently monitor updates to the Adobe AD0-E903 exam questions by Adobe. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the Adobe Workfront Project Manager Professional exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by Adobe in their Adobe AD0-E903 exam. These outdated questions lead to customers failing their Adobe Workfront Project Manager Professional exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the Adobe AD0-E903 exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

What are two characteristics of a Group in Workfront? (Choose two.)

Show Answer Hide Answer
Correct Answer: C, D

Groups in Adobe Workfront serve as organizational entities that can be associated with specific Companies or Projects to manage workflows or permissions more effectively. Additionally, each Group can have a Group Administrator assigned, who is responsible for managing the group's settings, permissions, and workflows. These roles and associations help in structuring how work and permissions are allocated across different teams or departments.


Question No. 2

A creative team accesses their assigned work in a My Tasks list report. The team would like to easily see any New tasks highlighted for visibility. How can the project manager accommodate the team's request?

Show Answer Hide Answer
Correct Answer: D

To meet the team's request for highlighting new tasks, the most effective solution is to create a View that uses Column Rules. These rules allow for conditional formatting based on task criteria, such as highlighting new tasks in a specific color for easy identification. This approach enhances visibility without requiring the creation of filters or new reports, and it makes it easier for users to see relevant tasks within their existing task lists.


Question No. 3

Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?

Show Answer Hide Answer
Correct Answer: A

The Projected Date in Adobe Workfront is dynamically calculated based on the progress of the task, any task constraints, and its dependencies. This date provides a more accurate reflection of when a task is likely to be completed, considering the current progress and any updates to predecessor tasks. On the other hand, the Planned Date refers to the originally scheduled completion date, and the Estimated Date is not manually entered but inferred from system calculations.


Question No. 4

A copywriter wants to see his incomplete tasks for projects to which he is assigned.

Which steps should the project manager take to create a custom Workfront report with this information?

Show Answer Hide Answer
Correct Answer: C

To filter tasks that are incomplete and assigned to a specific user, the correct approach is to create a Task report, then filter by Task Status that is 'Not Equal' to Complete. Additionally, the Assignment filter should include the user's name to ensure only tasks assigned to the specified copywriter are shown.


Question No. 5

The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.

Which task settings should be configured to meet these requirements?

Show Answer Hide Answer
Correct Answer: A

In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate 'Duration' and use 'Finish-Start' dependencies. The task's duration is key to determining the time allowed for its completion. The 'Finish-Start' dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a 'Finish-Start' dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.