AACE International AACE-PSP Practice Exam Questions & Answers

7 Free Questions · Last reviewed: October 23, 2026 · Prepared & Reviewed by the ValidExamDumps Editorial Team

Exam Facts

AACE International AACE-PSP Exam Details

Key details for this exam, checked against the published exam outline

216 Practice Questions (Our Bank)
300 minutes Exam Duration
70% Passing Score
Exam Code
AACE-PSP
Full Name
Planning and Scheduling Professional (PSP) Exam
Issuing Body
AACE International
Question Format (Our Bank)
Multiple Choice
Official Exam Fee
USD 500 (AACE members), USD 625 (non-members)
Delivery
Computer-based online exam at Kryterion exam center
Eligibility
Documented experience and education verified. submit application 45 days in advance. must take exam within 6 months of registration
Validity
3 years
Practice Questions

Free AACE-PSP Practice Questions

Each question shows the correct answer and an explanation of why it is right

VA
ValidExamDumps Editorial Team Every question and its answer is checked by our AACE-PSP exam preparation team, who also write the explanation shown with each one. How we research and review these pages

The Scope of Work divides the major deliverables into smaller more manageable components for all of the following EXCEPT to:

Correct Answer: D
Explanation A hammock activity spans from the start of the first activity to the end of the last activity in a series, capturing their total duration. To construct this theoretically, you calculate the duration from the early start of activity 6001 through the late finish of activity 6003. This requires performing forward and backward pass calculations to determine the exact timeframe. The 267-day duration represents this complete span. Other options would result from incomplete or incorrect calculations of the hammock's time boundaries.

In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?

Correct Answer: A
Explanation

Time-Scaled Value for Reporting Intervals:

BCWS (Budgeted Cost of Work Scheduled) is plotted over time to represent the planned expenditure at specific intervals.

BCWS provides the basis for schedule and cost performance comparisons.

Evaluation of Other Options:

B: BCWP is used to track actual progress.

C: SPI is a ratio, not a time-scaled value.

D: Actual cost of work scheduled is not a standard metric in earned value analysis.

Verification with PSP Guidelines: The PSP Study Guide identifies BCWS as essential for time-scaled earned value analysis (Ref: PSP Study Guide, Chapter 1D: Earned Value Analysis).

The BEST reason to use multiple calendars is to:

Correct Answer: A
Explanation

Purpose of Multiple Calendars:

Multiple calendars account for varied work/non-work periods among resources, regions, or activities, accurately representing project execution.

Evaluation of Other Options:

B, C, D: These may be secondary benefits but are not the primary reason.

Verification with PSP Guidelines: The PSP Study Guide emphasizes the importance of calendars for realistic scheduling (Ref: PSP Study Guide, Chapter 2A: Calendars and Constraints).

Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?

Correct Answer: C
Explanation

The column volume is 2,000 cubic feet (56.64 cubic meters), and each lift using a 1.75 cubic yard bucket corresponds to: Liftsrequired=Columnvolume(cubicyards)Bucketcapacity(cubicyards)\text{Lifts required} = \frac{\text{Column volume (cubic yards)}}{\text{Bucket capacity (cubic yards)}} Liftsrequired=Bucketcapacity(cubicyards)Columnvolume(cubicyards) Convert 56.64 cubic meters to cubic yards: 56.641.308=74.1456.64 \times 1.308 = 74.1456.641.308=74.14. Liftsrequired=74.141.75133lifts.\text{Lifts required} = \frac{74.14}{1.75} \approx 133 \text{ lifts}.Liftsrequired=1.7574.14133lifts.

Reference: PSP Study Guide, Section 1.3.7 -- Resource Calculations and Allocation, which emphasizes unit conversions and resource management.

Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

Correct Answer: C
Explanation

Activities not on the critical path are those with positive float, meaning they can be delayed without affecting the overall project completion time. The determination of such activities requires performing a forward and backward pass calculation as per CPM (Critical Path Method) analysis principles (PSP Study Guide, Section 2.2.4, 'Relationships').

For example:

Identify the critical path by analyzing total float values (typically, critical path activities have zero total float).

Exclude activities that do not fall on the critical path.

Which of the following statements is true?

Correct Answer: A
Explanation

Understanding Float:

Network Float: The shared amount of time that non-critical activities can be delayed without affecting the project completion date.

Float ownership is not exclusive unless explicitly stated in the contract.

Evaluation of Options:

Option B: Incorrect. Total float does not belong solely to the contractor unless stated.

Option C: Incorrect. Total float is not exclusively owned by the owner unless stated in the contract.

Option D: Incorrect. Free float is tied to specific activities and not shared.

Option A: Correct. In the absence of specific contract terms, network float is generally shared.

Determine the correct formula and date for the late start for Activity 9001.

Correct Answer: D
Explanation

Activity Details (9001 - 'Spillway - Concrete'):

Duration: 175 days in the Normal schedule.

To calculate Late Start (LS), the Late Finish (LF) is required. LS is calculated by subtracting the activity's duration from the LF.

Formula for Late Start (LS): LS = LF.9001 - Dur.9001.

Date Calculation:

Late Finish (LF.9001) = 11-20-02 (given or derived).

Apply the formula: LS.9001 = LF.9001 - Dur.9001 = 11-20-02 - 175 days.

Cross-Verification of Dates:

After subtracting 175 days, LS.9001 = 11-20-02.

Cross-Verification with Answer Options:

Option A: Incorrect. EF (Early Finish) is not needed for this calculation.

Option B: Incorrect. Uses LS and Dur incorrectly without connecting to LF.

Option C: Incorrect. Data provided is sufficient.

Option D: Correct. Matches both the formula and the date calculation.


PSP Study Guide (2019), Section 2A -- Schedule Development, Subsection on Backward Pass Calculations.

AACE Recommended Practices, RP 10S-90, discussing Late Start and Late Finish calculations.

Full Access

Get the complete AACE-PSP question set

  • 216 questions covering all exam domains
  • Correct answers with explanations, like the free questions above
  • PDF and online practice test
  • 90 days of free updates
Starting from 50% OFF
$20 $40
Get Full Access

One-time payment · Instant download

Study Guide

What the AACE International AACE-PSP Exam Covers

Exam domains verified against: Official AACE International AACE-PSP exam guide, last checked October 2026.

Domain 1: Basic Development Scheduling and Planning

Planning data, inputs, constraints, and deliverables form the foundation for schedule development. This section tests understanding of how to identify, organize, and document the baseline information required before creating a project network or timeline.

Sample questions from this domain above: Q3Q4Q5

Domain 2: Practical Exercise

Real-world network calculations and critical path analysis under time pressure. Candidates work through forward and backward pass calculations, float determination, and identify how constraint changes ripple through the schedule.

Sample questions from this domain above: Q1Q2

Domain 3: Planning and Scheduling Applications

Input information from planning, building schedules, maintaining, and managing schedules. Candidates update, predict, and examine schedules of related projects, applying scheduling concepts to multi-project environments and resource constraints.

Sample question from this domain above: Q7

Domain 4: Communication

One memo writing assignment based on a provided scenario. Candidates demonstrate the ability to communicate scheduling findings, recommendations, or issues in a professional written format to project stakeholders.

Sample question from this domain above: Q6

FAQ

AACE-PSP Exam FAQ

Common questions about the exam itself

What prior experience do I need to sit for the PSP exam?
AACE International requires documented work experience and education that meets their standards. You must submit your application 45 days in advance so they can verify your credentials. The application process includes review of your background to ensure you have relevant planning and scheduling experience.
How much time do I get in the PSP exam?
You have five hours total to complete all 119 questions and the one memo writing assignment. The exam combines multiple-choice questions on basic knowledge and scheduling applications with a practical exercise section where you perform network calculations.
What makes the practical exercise section so hard?
The practical exercise section requires you to calculate critical path, early and late dates, and float by hand under time pressure. Common mistakes happen when candidates miss a dependency or miscalculate float, and one error cascades through your entire calculation. Candidates who drill manual forward and backward pass calculations until the steps become automatic perform best.
Is the PSP exam open book or closed book?
The PSP exam is closed book. You cannot use textbooks, notes, or reference materials during the test. This means you need to memorize key definitions, relationship types, and calculation techniques beforehand.
What is the passing score for the PSP exam?
You need to achieve an overall average score of 70 percent or higher to pass. The final score is calculated by averaging your performance across all four domains, so weakness in one section can be offset by strength in another.
How long does the PSP certification stay valid?
The PSP certification is valid for three years from the date you pass the exam. After three years you must complete a recertification process to maintain your credential.
What is the cost to sit for the PSP exam?
AACE members pay USD 500 for the exam fee. Non-members pay USD 625. If you do not pass and need to retake within six months of your original registration, the resit fee is USD 250.
How long does it take to prepare for the PSP exam?
Realistic preparation typically requires several months of consistent study combined with hands-on experience in scheduling. Most candidates benefit from working through the PSP Study Guide, memorizing the required definitions and frameworks, and completing multiple practice schedule exercises to build speed and accuracy in the practical calculation sections.
What job roles does PSP certification lead to?
PSP certified professionals typically work as project planners, schedule managers, or project controls specialists across industries such as construction, engineering, aerospace, manufacturing, and software development. The certification demonstrates expertise in planning, scheduling, and project control that employers value for roles requiring precise project timeline management.
How does the PSP exam differ from the CCP certification?
The PSP exam focuses specifically on planning, scheduling, and project controls, making it narrower in scope than the CCP which covers cost engineering broadly. Both are AACE certifications accredited by CESB, but PSP candidates can pursue it without holding a CCP first.