Free AACE International AACE-PSP Exam Actual Questions

The questions for AACE-PSP were last updated On Jun 12, 2025

At ValidExamDumps, we consistently monitor updates to the AACE International AACE-PSP exam questions by AACE International. Whenever our team identifies changes in the exam questions,exam objectives, exam focus areas or in exam requirements, We immediately update our exam questions for both PDF and online practice exams. This commitment ensures our customers always have access to the most current and accurate questions. By preparing with these actual questions, our customers can successfully pass the AACE International Planning & Scheduling Professional (PSP) Exam exam on their first attempt without needing additional materials or study guides.

Other certification materials providers often include outdated or removed questions by AACE International in their AACE International AACE-PSP exam. These outdated questions lead to customers failing their AACE International Planning & Scheduling Professional (PSP) Exam exam. In contrast, we ensure our questions bank includes only precise and up-to-date questions, guaranteeing their presence in your actual exam. Our main priority is your success in the AACE International AACE-PSP exam, not profiting from selling obsolete exam questions in PDF or Online Practice Test.

 

Question No. 1

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

Show Answer Hide Answer
Correct Answer: A

Question No. 2

Using the normal schedule, what is the owner's total cost of the project?

Show Answer Hide Answer
Correct Answer: D

Question No. 3

An earned value-based project control system can use either of which two budgets as the basis of its calculations?

Show Answer Hide Answer
Correct Answer: A

Question No. 4

Project schedules help control all of the following EXCEPT for_____________________.

Show Answer Hide Answer
Correct Answer: A

Question No. 5

What is a key first step in developing a critical path method schedule?

Show Answer Hide Answer
Correct Answer: D